Plan of day

Date
Superintendent
  • +
Crew
  • +
Track Allocation
  • +
Trucking
  • +
Schedule
  • +
Shift
  • +
Date
Superintendent
Crew
Planned Task
Safety/Quality/Environment
Track Allocation
Trucking
Deliveries
Schedule
Shift
Yesterday's PF
Tomorrow's PF
Chainage
2026-08-24
Brandon
Durisol
Phase 2 & 3 (NWB 9s)

- Delivery of panels @ 1pm
- Delivery of garbage bin
- Crew to install final 42 panels of 9s
Utilities (ATMS & WM), L&R, MOT, HEI
Float Truck
Yes x2
Day
0
N/A
26+614
2026-08-24
JD
TG Carroll #1
O-train - O'Connor Overpass - EBL L3, L4 + Ramp Closures
MOT, HEI
2 crash trucks
9pm start
Night
0
N/A
27+874
2026-08-24
JD
B&M Pole Crew
Temporary Pole Removal
MOT, HEI
Bucket Truck, Pole Picker, 2 Pickups
9:30pm start
Night
0
N/A
27+874
2026-08-24
Cliff
Ethan/Kevin
- Chamberlain finish seacan inventory
- Install filter cloth and rip rap around CB's)
HEI, material handling
No
Day
0
N/A
27+898
2026-08-24
Cliff
Ethan/Kevin
Pond, install SOD
MOT
No
Day
0
N/A
27+985